Green OriGen+

Database / Climate Finance Database / ESIA Safeguards / FP015

FP015

Tuvalu Coastal Adaptation Project (TCAP)

View full project

Country

Tuvalu

Region

Asia and the Pacific

Sector

Public sector

Approval Year

2016

esia_safeguards

2 rows

esia_idcanonical_project_idesia_document_idreview_stagesafeguard_frameworksafeguard_categorybiodiversity_impact_flagresettlement_required_flagindigenous_peoples_flaglabor_risk_flagmitigation_measures
GCF_FP015_ESIA_001GCF_FP015GCF_FP015_DOC_013Appraisal (pre-approval)UNDP Social and Environmental Standards (SES)Category Btruefalse--Project employs a hybrid grey-green approach combining ecosystem-based measures (coral reef protection, seagrass protection/restoration) with hard engineering (concrete and rock revetments, sea walls) and soft measures (beach nourishment). An Environmental and Social Management Plan (ESMP) was required as a condition of GCF Board approval (decision B.23/12). National capacity for resilient coastal management is being developed. Coastal ecosystem initiatives are integral to the project design to reduce wave action impacts on key infrastructure.
GCF_FP015_ESIA_002GCF_FP015GCF_FP015_DOC_005Post-approval / ImplementationUNDP Social and Environmental Standards (SES)Category B----The post-approval ESS report (March 2022) confirms UNDP disclosed the full and complete environmental and social impact assessment (ESIA) and updated environmental and social management plan (ESMP) as required by GCF Board decision B.23/12, condition (ii)(iv), prior to the fourth disbursement of GCF proceeds.

Field Evidence

safeguard_categoryconfidence: 1method: direct_structured

Category B

safeguard_frameworkconfidence: 0.85method: derived

UNDP Social and Environmental Standards (SES)

review_stageconfidence: 0.9method: derived

Appraisal (pre-approval)

biodiversity_impact_flagconfidence: 0.7method: derived

true

resettlement_required_flagconfidence: 0.6method: derived

false

indigenous_peoples_flagconfidence: 0method: derived

-

labor_risk_flagconfidence: 0method: derived

-

mitigation_measuresconfidence: 0.8method: derived

Project employs a hybrid grey-green approach combining ecosystem-based measures (coral reef protection, seagrass protection/restoration) with hard engineering (concrete and rock revetments, sea walls) and soft measures (beach nourishment). An Environmental and Social Management Plan (ESMP) was required as a condition of GCF Board approval (decision B.23/12). National capacity for resilient coastal management is being developed. Coastal ecosystem initiatives are integral to the project design to reduce wave action impacts on key infrastructure.

safeguard_categoryconfidence: 1method: direct_structured

Category B

review_stageconfidence: 0.95method: derived

Post-approval / Implementation

mitigation_measuresconfidence: 0.9method: llm_extracted

The post-approval ESS report (March 2022) confirms UNDP disclosed the full and complete environmental and social impact assessment (ESIA) and updated environmental and social management plan (ESMP) as required by GCF Board decision B.23/12, condition (ii)(iv), prior to the fourth disbursement of GCF proceeds.

safeguard_frameworkconfidence: 0.85method: derived

UNDP Social and Environmental Standards (SES)

biodiversity_impact_flagconfidence: 0method: derived

-

resettlement_required_flagconfidence: 0method: derived

-

indigenous_peoples_flagconfidence: 0method: derived

-

labor_risk_flagconfidence: 0method: derived

-