risk_structure

Climate Resilient Infrastructure Mainstreaming (CRIM)

risk_idcanonical_project_idfinancing_component_idrisk_typerisk_bearerrisk_severitymitigation_mechanismmitigation_instrument_idresidual_risk_level
GCF_FP004_RISK_001GCF_FP004Implementation delayProject (LGED / KfW / GCF)HighExtension of project timeline by two years recommended; agile project management methods recommended to replace milestone framework; quarterly/semi-annual milestone planning; improved coordination between KfW and LGED on review timelines.
GCF_FP004_RISK_002GCF_FP004Staff recruitment and retentionConsultants (IDC and DMS)HighInternational experts to show greater presence or delegate tasks to national experts; improved staffing scheme; appointment of new IDC Team Leader with stakeholder approval.
GCF_FP004_RISK_003GCF_FP004GCF_FP004_FIN_001Cost escalation (construction materials)Project / GCF financingMediumReduction in scope of infrastructure components unless additional funding provided; potential shifting of budget savings from CReLIC component to infrastructure components.
GCF_FP004_RISK_004GCF_FP004Institutional development failureLGED / GCFHighQuick institutionalization of CReLIC as a staff unit under the Chief Engineer; co-creation of roadmap with LGED and consultants; assign LGED capacities and incentives for staff to engage in output development.
GCF_FP004_RISK_005GCF_FP004Coordination and communicationLGED / KfW / ConsultantsMediumIntroduction of Q&A sessions on KfW feedback; improved communication on submission timelines; introduction of standard meeting structure (progress, plan, challenges); more frequent CCC meetings for senior management updates.

Field Evidence

risk_typeconfidence: 0.85method: pdf_text

Implementation delay

risk_bearerconfidence: 0.8method: pdf_text

Project (LGED / KfW / GCF)

risk_severityconfidence: 0.75method: pdf_text

High

mitigation_mechanismconfidence: 0.8method: pdf_text

Extension of project timeline by two years recommended; agile project management methods recommended to replace milestone framework; quarterly/semi-annual milestone planning; improved coordination between KfW and LGED on review timelines.

risk_typeconfidence: 0.85method: pdf_text

Staff recruitment and retention

risk_bearerconfidence: 0.8method: pdf_text

Consultants (IDC and DMS)

risk_severityconfidence: 0.75method: pdf_text

High

mitigation_mechanismconfidence: 0.8method: pdf_text

International experts to show greater presence or delegate tasks to national experts; improved staffing scheme; appointment of new IDC Team Leader with stakeholder approval.

risk_typeconfidence: 0.85method: pdf_text

Cost escalation (construction materials)

risk_bearerconfidence: 0.75method: pdf_text

Project / GCF financing

risk_severityconfidence: 0.65method: pdf_text

Medium

mitigation_mechanismconfidence: 0.8method: pdf_text

Reduction in scope of infrastructure components unless additional funding provided; potential shifting of budget savings from CReLIC component to infrastructure components.

risk_typeconfidence: 0.85method: pdf_text

Institutional development failure

risk_bearerconfidence: 0.8method: pdf_text

LGED / GCF

risk_severityconfidence: 0.75method: pdf_text

High

mitigation_mechanismconfidence: 0.8method: pdf_text

Quick institutionalization of CReLIC as a staff unit under the Chief Engineer; co-creation of roadmap with LGED and consultants; assign LGED capacities and incentives for staff to engage in output development.

risk_typeconfidence: 0.85method: pdf_text

Coordination and communication

risk_bearerconfidence: 0.8method: pdf_text

LGED / KfW / Consultants

risk_severityconfidence: 0.65method: pdf_text

Medium

mitigation_mechanismconfidence: 0.8method: pdf_text

Introduction of Q&A sessions on KfW feedback; improved communication on submission timelines; introduction of standard meeting structure (progress, plan, challenges); more frequent CCC meetings for senior management updates.